Mobilis wants to build autonomously on the water treatment plant for two weeks

How Mobilis kept building a water treatment plant in Beuningen: two weeks of autonomous operation on the CleanStar, with electric equipment and no nitrogen deposition.

Insufficient grid capacity for
heavy electric equipment

Insufficient grid capacity for heavy electric construction equipment

Problem

Mobilis is building a water treatment plant in Beuningen, fully electric and with ultra-low on-site emissions. The bottleneck: the existing grid connection simply didn’t provide enough capacity for the heavy electric equipment required.

CleanStar 250
generator

Solution

The CleanStar 250 provided the solution: 250 kW of continuous power, no nitrogen deposition, and enough energy to keep the construction site running autonomously for two weeks. This kept the project on schedule, without relying on the grid.

No nitrogen deposition, net-zero CO2, independently tested.

It works similarly to traditional diesel solutions, but with ultra-low emissions. Ready to deploy immediately, with no long waits for grid upgrades.

bryntell mobilis case study

A first
of its kind

A first of its kind

Result

Mobilis was the first civil engineering contractor to successfully use the Bryntell CleanStar on a construction project. This confirms that the solution proves its value in practice, on an active construction site.

Bryntell generator road construction project

Calculate your project
with the Bryntell specialists

Custom quote

Let’s meet!

Let’s
meet!

Clean energy, flexibly deployed
anytime, anywhere

Let’s meet!

Let’s
meet!

Clean energy, flexibly deployed
anytime, anywhere

Let’s meet!

Clean energy, flexibly deployed
anytime, anywhere